Downtown Revitalization

The City of Fate's 2018 Downtown Revitalization project for a walkable destination will include mixed-use developments such as retail, restaurants, boutiques, live-above lofts, street improvements, widened sidewalks, streetscape, landscape, and more!

Are you or someone you know an entrepreneur, restaurateur, small business owner, or developer that’s looking for an incredible opportunity within our downtown?

Please send an email to Justin Weiss, Assistant City Manager, to express your interest. 

Downtown 3-Story Rendering(PNG)

Click on the image below to download a PDF presentation related to the downtown revitalization.

Downtown Revitalization Overview (PNG)

Construction Timeline for Public Improvements:

Phase 1 - 145 Days (October 22nd to May 10th)
Sanitary Sewer (William Crawford)
Sanitary Sewer (Greenhill)
Water Line (William Crawford)
Water Line (Greenhill)
Storm on Fate Main Place to Brown Ave
Storm on Old Town St (new road)
Asphalt Removal (William Crawford / Greenhill / Brown / Old Town St)
Excavation
Subgrade Prep
Lime Stabilization
Paving
Asphalt Transition (William Crawford)
Backfill
Stamped Concrete
Driveway
Sidewalk
Backfill / Cleanup

Phase 2 - 118 Days (May 10th to October 22nd)
Waterline (Fate Main St.)
Asphalt Removal (Fate Main St.)
Excavation
Subgrade Prep
Lime Stabilization
Paving 1/2 Road at a Time (Fate Main St.)
Grade Prep
Paving 1/2 Road at a Time (Fate Main St.)
Asphalt Transition on Fate Main St.
Backfill
Stamped Concrete
Driveway
Sidewalk
Landscape
Final Clean Up

Who's coming to Downtown?

Check back often as we continue to list the businesses who have announced they are coming to Downtown Fate!

Downtown 3-Story Mixed Use Ad (PNG)

The Lofts (PNG)

Restaurant Concept (PNG)

LAFAYETTE PLACE (PNG)

Four Czechs Bakery Announcement (JPG) Opens in new window